Policy Update
Sudeshna Dutta
Background
India’s clean energy transition has accelerated sharply over the past decade, with total installed power capacity reaching 552 GW by July 2026 (up from 249 GW in 2014) and non-fossil fuel capacity surpassing 300.50 GW—accounting for over 54% of total installed capacity. As India progresses toward its intermediate target of 500 GW of non-fossil fuel capacity by 2030 and an expanded national ambition of 900 GW by 2035, the primary systemic bottleneck has shifted from power generation to grid evacuation, sub-transmission congestion, and intermittency management. Renewable energy (RE) generation—predominantly solar and wind—is geographically concentrated in resource-rich states (such as Rajasthan, Gujarat, Tamil Nadu, Karnataka, Maharashtra, Andhra Pradesh, and Madhya Pradesh) and exhibits pronounced diurnal and seasonal variability.
Originating from a 2012 grid-integration study by the Power Grid Corporation of India Limited (PGCIL) and formally launched in 2015, the Green Energy Corridor (GEC) programme was conceived to synchronize the build-out of high-voltage transmission infrastructure with variable renewable generation. While Phase-I (approved in 2015) and Phase-II (approved in January 2022 for Intra-State Transmission Systems and October 2023 for the Ladakh Inter-State Transmission System) focused predominantly on building physical transmission lines and substations, the rapid penetration of solar PV created acute midday curtailment risks alongside steep evening ramping requirements during non-solar hours. To resolve this structural mismatch, the Union Cabinet chaired by Prime Minister Narendra Modi approved the Green Energy Corridor Phase-III (GEC-III) scheme on September 30, 2026. GEC-III represents a paradigm shift from pure wire-and-transformer expansion to an integrated “transmission-plus-storage” architecture designed to evacuate up to 135 GW of renewable energy across Indian States and Union Territories by FY 2032–33.
| Policy Parameter | GEC Phase-I (InSTS) | GEC Phase-II (InSTS) | GEC Phase-II (ISTS – Ladakh) | GEC Phase-III (InSTS + BESS) |
| Year of Cabinet Approval | 2015 | January 2022 | October 2023 | September 30, 2026 |
| Target RE Evacuation Capacity | ~24 GW | ~20 GW | 13 GW | Up to 135 GW |
| Geographic Scope | 8 RE-rich States | 7 States | UT of Ladakh to National Grid | Pan-India (All States & UTs) |
| Physical Transmission Target | 9,700 ckm lines; 22,600 MVA substations | 10,750 ckm lines; 27,500 MVA substations | 1,268 ckm lines; two 5,000 MW HVDC terminals | State-specific InSTS expansion for 135 GW |
| Dedicated BESS Integration | Nil | Nil | 12 GWh (12,000 MWh) | 50 GWh across state grid nodes |
| Total Financial Outlay | ₹10,141.68 crore | ₹12,031.33 crore | ₹20,773.70 crore (excl. IDC) | ₹1,86,405 crore |
| Central Fiscal Support (CFA/CFS) | ₹4,056.67 crore (40% grant) | ₹3,970.34 crore (33% CFA) | ₹8,309.48 crore (40% CFA) | ₹54,082 crore (CFS/CFA) |
| Target Completion Timeline | Extended up to FY 2025–27 | March 2026 | FY 2029–30 | FY 2032–33 |
Functioning
GEC-III operates through a bifurcated asset architecture that pairs Intra-State Transmission System (InSTS) expansion with utility-scale Battery Energy Storage Systems (BESS), backed by targeted fiscal intervention from the Union Government. Of the total sanctioned project outlay of ₹1,86,405 crore, ₹1,36,378 crore is earmarked for developing intra-state high-voltage transmission lines and pooling substations, while ₹50,000 crore is dedicated exclusively to deploying 50 GWh of grid-scale BESS. The remaining balance accounts for ancillary administrative, monitoring, and technical facilitation components within the aggregate outlay.
To ensure tariff affordability, the Union Government has sanctioned ₹54,082 crore in Central Financial Support (CFS) / Central Financial Assistance (CFA)—representing roughly 29.01% of the total outlay—which directly subsidizes capital expenditure so that State Electricity Regulatory Commissions (SERCs) do not pass heavy network expansion costs onto retail consumers through higher intra-state transmission charges.
Institutional execution under GEC-III is decentralized to State Transmission Utilities (STUs), which serve as the principal nodal implementing agencies across participating States and Union Territories. To enforce capital discipline and timely commissioning, MNRE has mandated distinct procurement tracks based on asset classification. All greenfield intra-state transmission projects must be awarded through Tariff Based Competitive Bidding (TBCB), wherein selected Transmission Service Providers (TSPs) develop and run assets on a Build-Own-Operate-Maintain (BOOM) model. Conversely, brownfield upgradation, reconductoring, and existing substation strengthening works are executed on a Cost Plus Basis (CPB) by STUs to expedite localized bottleneck removal where competitive bidding is structurally unviable. Meanwhile, the 50 GWh BESS component is engineered for flexible siting—either co-located at renewable energy generator/developer pooling stations or positioned at critical transmission load nodes—where batteries store surplus midday solar energy, provide millisecond-level frequency regulation, prevent peak-hour curtailment, and discharge power during evening peak and non-solar hours. (Press Information Bureau, 2026)
| Component / Track | Financial Allocation | Procurement & Delivery Mode | Implementing / Operating Entity | Core Technical & Regulatory Function |
| InSTS Greenfield Works | Part of ₹1,36,378 crore InSTS outlay | Tariff Based Competitive Bidding (TBCB) under BOOM model | STUs (Nodal Agency) & Private/Public TSPs | Construct new intra-state lines & pooling substations to evacuate up to 135 GW RE. |
| InSTS Brownfield Works | Part of ₹1,36,378 crore InSTS outlay | Cost Plus Basis (CPB) under SERC tariff norms | State Transmission Utilities (STUs) | Upgrade existing lines, bays, and transformers to decongest local state grids. |
| Battery Energy Storage Systems (50 GWh) | ₹50,000 crore | Competitive Bidding / Storage Service Contracts | RE Developers, Generators, & Grid Operators | Absorb midday RE surplus, mitigate curtailment, stabilize frequency, and supply non-solar peak demand. |
| Central Financial Support (CFS / CFA) | ₹54,082 crore (Grant support) | Direct Central Capital Grant via MNRE | MNRE disbursing to STUs / Implementing Agencies | Offset intra-state transmission charges and contain end-user electricity tariffs. |
Performance
Because GEC-III was approved on September 30, 2026 with an implementation horizon extending to FY 2032–33, its performance baseline must be evaluated through the empirical track record of GEC Phase-I and Phase-II, alongside national grid readiness benchmarks. Under InSTS GEC Phase-I (sanctioned at ₹10,141.68 crore with 40% MNRE grant and 40% KfW concessional debt), STUs across eight renewable-rich states achieved substantial physical build-out: against a target of 9,700 ckm of transmission lines and 22,600 MVA of substation capacity, 9,135 ckm of lines (94.2%) and 21,313 MVA of substations (94.3%) were constructed and charged by late 2024, advancing toward ~9,856 ckm and ~24,300 MVA under revised state packages. Four of the eight states—Rajasthan, Madhya Pradesh, Karnataka, and Tamil Nadu—completed 100% of their Phase-I packages ahead of extended schedules, while Andhra Pradesh, Himachal Pradesh, Gujarat, and Maharashtra required timeline extensions into 2025–2027 due to localized execution hurdles. Simultaneously, the Inter-State Transmission System (ISTS) component of Phase-I (3,200 ckm and 17,000 MVA implemented by PGCIL) was fully commissioned in March 2020, and 11 Renewable Energy Management Centres (REMCs) were operationalized across Southern, Western, and Northern load dispatch hierarchies to provide real-time RE forecasting.
InSTS GEC Phase-II—sanctioned in January 2022 at ₹12,031.33 crore (with 33% CFA of ₹3,970.34 crore) across Gujarat, Himachal Pradesh, Karnataka, Kerala, Rajasthan, Tamil Nadu, and Uttar Pradesh to add 10,750 ckm of lines and 27,500 MVA of transformation capacity for ~20 GW of RE—transitioned through tendering and construction toward its March 2026 baseline schedule, subject to state-level scope revisions approved by MNRE. Nationally, India’s aggregate transmission network reached 4,94,732 ckm of lines and 13,50,953 MVA of transformation capacity by April 2025, with inter-regional transfer capacity expanding by 230% since 2014 to 1,18,740 MW. GEC-III builds directly on these institutional learnings: by scaling target RE evacuation nearly six-fold over Phase-I (from 24 GW to 135 GW) and embedding 50 GWh of BESS—which addresses roughly 21.2% of the Central Electricity Authority’s (CEA) projected national requirement of over 236 GWh of BESS by FY 2031–32—GEC-III corrects the structural omission of storage in earlier intra-state phases.
| Performance Metric | GEC Phase-I (InSTS) Benchmark | GEC Phase-II (InSTS) Benchmark | GEC Phase-III (InSTS + BESS) Target |
| RE Evacuation Scale | ~24 GW (16.4+ GW grid-connected early) | ~20 GW across 7 States | Up to 135 GW across all States/UTs |
| Physical Line & Substation Progress | 9,135 ckm / 21,313 MVA charged by Oct 2024 (~94% of initial target) | 10,750 ckm / 27,500 MVA under execution (baseline Mar 2026) | Multi-state InSTS build-out + 50 GWh BESS by FY 2032–33 |
| State Completion Variance | 4 states 100% complete; 4 states extended to 2025–2027 | Project scope revisions approved by MNRE for select states | Standardized TBCB (BOOM) for greenfield to enforce deadlines |
| Grid Flexibility & Storage | Relied on 11 REMCs & reactive compensation; zero BESS | Zero InSTS BESS (12 GWh restricted to Ladakh ISTS) | 50 GWh BESS (~21% of CEA’s 236+ GWh FY32 national need) |
Impact
The macroeconomic, technical, and environmental impacts of GEC-III span power system reliability, industrial policy, consumer tariff protection, and climate mitigation. Technically, integrating 50 GWh of BESS alongside 135 GW of intra-state evacuation capacity fundamentally alters the operational profile of variable renewable energy. By absorbing excess generation during peak solar irradiance and discharging during evening peak demand, GEC-III converts intermittent solar and wind output into firm, dispatchable power, drastically reducing renewable curtailment and lowering reliance on thermal coal plants for evening ramping and spinning reserves. Furthermore, strategic siting of BESS at congested intra-state substations shaves local peak loads, thereby deferring redundant high-voltage wire capital expenditure and enhancing voltage and frequency stability.
Economically and socially, the ₹54,082 crore Central Financial Support acts as a direct fiscal shield for retail electricity consumers and Distribution Companies (DISCOMs) by absorbing nearly 30% of capital costs and preventing sharp spikes in state transmission wheeling charges. On the industrial front, the ₹50,000 crore BESS allocation creates a guaranteed domestic demand pipeline of 50 GWh over seven years, catalyzing upstream investments in Advanced Chemistry Cell (ACC) battery manufacturing, power electronics, grid-forming inverters, and battery management systems under India’s Atmanirbhar Bharat manufacturing ecosystem. Employment generation is projected across two distinct waves: large-scale direct and indirect construction and engineering jobs during transmission corridor and substation erection, followed by long-term skilled technical employment in BESS operations, maintenance, and state-level REMC grid management. Strategically, GEC-III locks in the sub-transmission backbone required to achieve India’s 2030 (500 GW) and 2035 (900 GW) non-fossil capacity milestones while advancing India’s Nationally Determined Contributions (NDCs) and 2070 Net-Zero trajectory.
| Impact Dimension | Primary Mechanism under GEC-III | Quantified / Structural Outcome |
| Grid Reliability & Decarbonization | 135 GW InSTS evacuation + 50 GWh BESS peak-shifting & frequency response | Minimizes RE curtailment, displaces fossil-fuel peaking generation, and anchors 900 GW non-fossil target by 2035. |
| Consumer Tariff Protection | ₹54,082 crore Central Financial Support offsetting InSTS capex | Suppresses intra-state transmission tariff pass-through, keeping retail power affordable for households and industry. |
| Domestic Industrial Ecosystem | ₹50,000 crore dedicated procurement for 50 GWh grid-scale BESS | Accelerates domestic cell manufacturing, inverter assembly, and BESS supply-chain localization. |
| Employment & Human Capital | Multi-state TBCB/CPB civil works and long-term grid/BESS operations | Creates large-scale construction/manufacturing jobs plus permanent skilled O&M and grid-dispatch roles. |
Emerging Issues
Despite its transformative scale, GEC-III confronts four structural implementation risks that previously delayed GEC Phase-I and Phase-II. First, Right-of-Way (RoW) acquisition and land clearances remain the single largest cause of transmission schedule slippage in India. High-voltage intra-state corridors pass through agricultural land, ecologically sensitive zones, and rapidly urbanizing peri-urban belts, where disputes over land-value compensation, forest clearances, and wildlife corridor approvals routinely stall tower erection by 12 to 24 months. While TBCB shifts construction risk onto private TSPs, private developers cannot resolve statutory RoW bottlenecks without proactive state revenue-department intervention.
Second, state-level counterparty and DISCOM financial fragility poses commercial risks for both transmission and storage contracting. Many state DISCOMs suffer from high Aggregate Technical and Commercial (AT&C) losses and delayed payment cycles, which can elevate perceived credit risk for private TSPs and BESS operators bidding under long-term TBCB contracts. Third, global supply-chain concentration and raw material volatility threaten the ₹50,000 crore BESS rollout. India remains heavily import-dependent for processed lithium, cobalt, nickel, and battery-grade graphite—dominated by East Asian and Chinese refining ecosystems—exposing project timelines and capital costs to geopolitical export restrictions and commodity price swings. Fourth, technical and regulatory harmonization gaps persist at the state load dispatch level: integrating 50 GWh of distributed BESS requires anticipated updates to State Grid Codes, harmonized intra-state ancillary-service market rules and tariff structures for battery charging and discharging, proposed grid-forming inverter standards (issued as draft regulations by the CEA for implementation from July 2027), and standardized, cyber-secure automated dispatch protocols across all State Load Despatch Centres (SLDCs).
| Emerging Risk Category | Root Structural Cause | Potential Policy & Execution Impact |
| Right-of-Way (RoW) & Land Delays | Fragmented state land compensation norms, forest/wildlife clearances, and urban encroachment | Delayed commissioning of InSTS lines, stranding newly built RE generation capacity. |
| STU & DISCOM Counterparty Risk | Weak balance sheets of state utilities and historic payment delays to private developers | Higher risk premiums in TBCB bids, reducing private sector participation in weaker states. |
| BESS Supply-Chain Vulnerability | Heavy import reliance on refined lithium, nickel, cobalt, and cell components | Capex overruns beyond the ₹50,000 crore allocation or commissioning delays toward FY 2032–33. |
| Grid Code & Market Design Gaps | Legacy SLDC operating rules unsuited for bi-directional battery arbitrage and ancillary services | Sub-optimal utilization of the 50 GWh BESS fleet and persistent midday RE curtailment. |
Way Forward
To ensure GEC-III achieves full physical and commercial operationalization by FY 2032–33 without repeating the timeline extensions of earlier phases, MNRE, the Ministry of Power, and participating State Governments should execute five targeted policy interventions:
- Standardize RoW Compensation and Mandate Pre-Bid Clearances: States should adopt uniform, market-linked RoW compensation guidelines modeled on the Ministry of Power’s updated RoW framework, paired with digital single-window clearance portals. For TBCB greenfield packages, STUs should secure preliminary forest/wildlife clearances and geospatial route approvals prior to issuing Request for Proposals (RfPs) so private TSPs can begin construction immediately upon financial close.
- De-Risk State Counterparty Exposure via Payment Security Mechanisms: To attract competitive private capital into TBCB transmission and BESS tenders across all States and UTs, GEC-III guidelines should mandate tripartite payment security mechanisms—combining revolving Letters of Credit (LCs), state-level escrow accounts, and Central Financial Support disbursement milestones linked to timely STU/DISCOM tariff settlement.
- Synchronize BESS Tenders with Domestic Value Addition and Multi-Chemistry Diversification: MNRE should align GEC-III’s 50 GWh BESS procurement with the Production Linked Incentive (PLI) scheme for Advanced Chemistry Cells by introducing phased Domestic Content Requirements (DCR) for battery pack assembly, thermal management, and power conversion systems, while keeping technology specifications chemistry-agnostic (allowing Lithium Iron Phosphate, Sodium-ion, and Flow batteries) to mitigate lithium import shocks.
- Reform State Grid Codes and Ancillary Service Markets: The Central Electricity Regulatory Commission (CERC) and SERCs should notify harmonized state-level BESS operational regulations by FY 2027–28, enabling stacked revenue streams (energy time-shifting, primary/secondary frequency response, and black-start services) and ensuring seamless coordination between SLDCs, REMCs, and BESS Energy Management Systems.
- Enforce Digital Twin Monitoring and Milestone-Linked CFA Tranches: MNRE should link the release of the ₹54,082 crore Central Financial Support to real-time satellite/GIS construction tracking and mandatory commissioning synchronization between RE generation parks, InSTS substations, and co-located BESS nodes.
| Strategic Pillar | Actionable Policy Measure | Responsible Institutions | Target Timeline |
| 1. RoW & Permitting Reform | Adopt standardized RoW compensation & pre-bid statutory clearances for TBCB packages | State Revenue/Forest Depts, STUs, Ministry of Power | FY 2026–27 |
| 2. Financial De-Risking | Establish tripartite Payment Security Mechanisms (LCs + Escrow) for TSPs and BESS operators | MNRE, State Energy Depts, REC / PFC | FY 2026–27 |
| 3. Supply-Chain Resilience | Align 50 GWh BESS tenders with ACC-PLI DCR norms and chemistry-neutral specifications | MNRE, Ministry of Heavy Industries, CEA | FY 2027–28 |
| 4. Regulatory & Market Design | Notify state BESS grid codes, ancillary service tariffs, and grid-forming inverter mandates | CERC, SERCs, CEA, POSOCO / Grid-India | FY 2027–28 |
| 5. Execution Governance | Link ₹54,082 crore CFA tranches to GIS milestone verification and generation-grid sync | MNRE, Central Electricity Authority (CEA) | Ongoing to FY 2032–33 |
Selected References and Important Links
- Central Electricity Authority. (2024). National Electricity Plan (Volume II): Transmission. Ministry of Power, Government of India. https://cea.nic.in/
- Drishti IAS. (2026, October 1). Green Energy Corridor Phase-III. https://www.drishtiias.com/daily-updates/daily-news-analysis/green-energy-corridor-phase-iii
- Energy-Storage.News. (2026, October 2). India approves US$19.3 billion Green Energy Corridor Phase III with 50GWh BESS. https://www.energy-storage.news/india-approves-us19-3-billion-green-energy-corridor-phase-iii-with-50gwh-bess/
- Ministry of New and Renewable Energy. (2026). Annual Report 2025–26. Government of India. https://mnre.gov.in/
- Ministry of Power. (2026). Transmission schemes and services: Green Energy Corridor (GEC) Phase-I & Phase-II. Government of India. https://www.powermin.gov.in/offerings/schemes-and-services/details/transmission-cDMyMTMtQWa
- Press Information Bureau. (2023, October 18). Cabinet approves Green Energy Corridor (GEC) Phase-II – Inter-State Transmission System (ISTS) for 13 GW Renewable Energy Project in Ladakh [Press Release ID: 1968733]. Ministry of New and Renewable Energy, Government of India. https://www.pib.gov.in/PressReleasePage.aspx?PRID=1968733
- Press Information Bureau. (2026, September 30). Cabinet approves Green Energy Corridor Phase-III scheme for Development of Intra-State Transmission System with Battery Energy Storage Systems [Press Release ID: 2316948 / 2316950]. Ministry of New and Renewable Energy, Government of India. https://www.pib.gov.in/PressReleaseDetail.aspx?PRID=2316948®=3&lang=1
- Prime Minister’s Office. (2026, September 30). Cabinet approves Green Energy Corridor Phase-III scheme for Development of Intra-State Transmission System with Battery Energy Storage Systems. Government of India. https://www.pmindia.gov.in/en/news_updates/cabinet-approves-green-energy-corridor-phase-iii-scheme-for-development-of-intra-state-transmission-system-with-battery-energy-storage-systems/
- Press Information Bureau, Government of India. (2026, September 30). Cabinet approves Green Energy Corridor Phase-III scheme for development of Intra-State Transmission System with Battery Energy Storage Systems [Press release]. Ministry of New and Renewable Energy. https://www.pib.gov.in/PressReleasepage.aspx?PRID=2316948
- The Hindu. (2026, October). Union Cabinet passes Green Energy Corridor. https://www.thehindu.com/business/union-cabinet-passes-green-energy-corridor/article71528006.ece
About the Author
Sudeshna Dutta is a second-year B.A. (Hons.) History student at Lady Shri Ram College for Women, University of Delhi. She is a Research & Editorial Intern at IMPRI (Impact and Policy Research Institute). Her academic and policy interests lie at the intersection of law & public policy, geoeconomics and history.
Acknowledgement
The author sincerely thanks the IMPRI team for their guidance and support throughout the preparation of this Policy Update. The author also acknowledges the valuable feedback and constructive suggestions provided by the reviewers, Aditi Bhuinyan, which helped improve the clarity, structure, and analytical depth of the article.
Disclaimer: All views expressed in the article belong solely to the author and not necessarily to the organization.